UPSC Civil ServicesPrelims2024General Studies Paper II (CSAT)

Question

QQ7. A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?

Options

  1. A 10%
  2. B (50/3)%
  3. C 20%
  4. D 25%
Show Answer

Correct Answer

C 20%

Model Answer

Answer: option C, as per UPSC's final answer key (Series A).